The World Bank will continue to pay for the controversial Sardar Sarovar
dam project on the Narmada River in India, ignoring warnings from its own
advisers. Earlier this year, a team commissioned by the bank to investigate
the scheme produced a damning report which concluded that there were 鈥榮erious
deficiencies鈥� in the project. Yet at a meeting last week, 59 per cent of
the bank鈥檚 executive directors voted to continue funding. The American,
German and Japanese directors voted against continuing support for the project.
The bank has done a lot of soul-searching over the dam project since
the review team presented its scathing report. At the time, its president,
Lewis Preston, issued a statement acknowledging problems with the project,
and promising 鈥榬emedial actions鈥� (This Week, 27 June). Last month, the bank鈥檚
management submitted a detailed plan for making changes in accordance with
the review鈥檚 findings.
But two weeks ago the leaders of the review team, Bradford Morse and
Thomas Berger, wrote to Preston claiming that the remedial plan 鈥榠gnores
or misrepresents the main findings鈥� of their review. The bank鈥檚 plan fails
to take into account specific points, including the unfair treatment of
people ousted to make room for what would be the largest canal ever built,
they say. The leaders of the review panel also say that the plan鈥檚 鈥榠ndifference
to the proper place and utility of environmental work is astonishing鈥�.
Advertisement
In reply, Preston wrote that he found the charge of misrepresentation
鈥榲ery disconcerting鈥�. He maintained that recent changes in the project made
by the Indian government and the states affected by the dam had been 鈥榲ery
constructive and justify a continuation of Bank support鈥� for the next few
months.
Meanwhile, an international coalition of nongovernmental organisations,
led by the Environmental Defense Fund in the US, wrote to the World Bank鈥檚
executive directors to say that not only does the bank鈥檚 plan not properly
address the findings of the review, it also fails 鈥榯o acknowledge the widespread
opposition and associated human rights abuses鈥�. They accuse the bank of
watering down its earlier demands and conditions for the resettlement and
rehabilitation of people affected by the dam. They suggest that the 鈥榗redibility
of the bank is at stake鈥� and called on the directors to withdraw support
for the project.
The bank will send a team to India next April to check how the new plan
is being implemented. It will then consider whether to continue funding
the project.